Rail replacement Details from Dec-2020 to Dec.-2024
Sl no Year Line & OHE Mast UP/DN Location RR/LR Rail Length (m) Curve/straight Remarks
1 9/10.06.2021 11/133-137 UP VW-VS LR 9 ULC-4 ulc 4
UP line New rail panel insert of 9 mtr
2 9/10.05.2024 VW/87-91 UP VW 3rd Siding RR 8.4 STRAIGHT 8.4 m For Chipping Removal
3 10/11.12.2020 13/221-223 UP KGM UP p/f RR 6 ULC-13 6 mtr Rail panel insert at KGM up
platform
4 20/21.12.2020 13/201-203 UP KGM UP p/f
point 02N
RR 7 STRAIGHT Approx 7 mtr rail panel insert ahed of
SRJ at point 2N RH side
5 21/22.12.2020 13/197-199 UP KGM UP p/f
point 02N
RH LEAD
RAIL
15 STRAIGHT 9 mtr 6 mtr ail insert main line &
diverson lead rail of point 2N
6 27/28.08.2021 14/165-167 UP KGM-CHK LR 8.4 ULC-14 8.4 m rail panel insert with removed 1
no chipping location .
7 11/12.07.2022-
30/31.08.2022
14/149-241 UP KGM-CHK RR 388.53 ULC-14 388.53 mtr New Rail insert for removed
chipping on rail head
8 9/10.11.2022 13/219-221 UP KGM-CHK RR 13.286 ULC-13 13.286 mtr new rail pannel insert for
removed pitted on rail & removed 2 no
9 02/03.09.2021 15/203-205 UP CHK-CWBR RR 8.5 ULC-15 8.5 m rail panel insert with removed 1
no fish plated chipping location .
10 21/22.06.2022 15/233-235 UP CHK-CWBR RR 8.247 ULC-15 8.247 mtr New Rail insert for removed
chipping on rail head
11 22/23.06.2022 15/85-87 UP CHK-CWBR RR 18 STRAIGHT 18 mtr New Rail insert for removed
chipping on rail head
12 27/28.06.2022 15/189-187 UP CHK-CWBR LR 11.2 ULC-15 11.2 mtr New Rail insert for removed
chipping on rail head
13 31/01.09.2021 16/123-125 UP CWBR-NDI RR 9 STRAIGHT 9 m rail panel insert with removed 1 no
fish plated chipping location .
14 01/02.09.2021 16/87-89 UP CWBR UP P/F RR 8.4 STRAIGHT 8.4 m rail panel insert with removed 1
no chipping location .
15 28/29.06.2022 16/123-127 UP CWBR-NDI LR 8.735 STRAIGHT 8.735 mtr New Rail insert for removed
chipping on rail head
16 23/24.09.2021 17/95-97 UP NDI-RCK RR 8.83 ULC-18 8.83 m rail panel insert with removed 1
no fish plated IMR & chipping location .
17 19/20.02.2022 18/27-29 UP NDI-RCK UP
P02P RH SRJ
RR 11.434 ULC-19 New extended leg 1:8.5 RH switch
replaced at P02P due to fracture of
18 26/27.02.2022 18/27-29 UP NDI-RCK LH 25 ULC-19 New extended leg 1:8.5 LH switch
replaced at P02P due to chipping of
19 06/07.07.2022 17/165-169 UP NDI-RCK LR 7.5 STRAIGHT 7.50 mtr New Rail insert for removed
chipping on rail head
20 16/17.03.2023 17/117-115 UP NDI-RCK LR 9.8 ULC-18 9.8 mtr new rail pannel insert for
removed chipping on rail head
21 07/08.02.2024 18/003-005 UP NDI-RCK RR 11.3 11.3 m rail insert
22 04/05.03.2024 18/23-25 UP NDI - RCK
UP line R lead rail of P02P
RR 5.827 ULC-19 5.827 m rail insert due to weld fracture
23 06/07.06.2024 17/227-229 UP NDI-RCK 18 ULC-19 18 M REPLACEMENT
24 30/31.01.2024 to
31/01.02.2024
18/33-39 UP RCK-PTCK RR 27.4 ULC-19 27.4 m Rail insert
25 21/22.04.2021 21/77-81 UP UDB-LKM RR 9.7 STRAIGHT Approx 9.7 mtr rail panel insert
26 10/11.08.2023 20/213-215 UP UDB-LKM LR 8.3 ULC-24 8.3 mtr Rail pannel insert
27 30/31.01.2023 25/57-59 UP INA - AIIMS LR 7.654 ULC-32 7.654 mtr new rail pannel insert and
removed fracture rail of flush butt weld
28 25/26.11.2023 to
26/27.11.2023
26/71-75 UP AIIMS-GNPK
UP RR
RR 24.97 STRAIGHT 24.97 mtr rail insert
29 8/9.03.2022 26/103-107 UP AIIMS-GNPK P 02U UP RR 10.8 STRAIGHT Insert 10.8 mtr rail pannel & removed DFWR Weld
30 10/11.03.2022 26/105-107 UP AIIMS-GNPK P 02U
GNPK
RR 11.4 STRAIGHT 11.400 mtr Rail insert for removrd of DFWR weld
31 17/18.08.2022 26/103-105 UP AIIMS- GNPK LR 8.87 STRAIGHT 8.87 mtr new rail pannel insert for
removed AT weld fracture
32 12/13.06.2022 30/191-193 UP MVNR- SAKT RR 8.403 ULC-40 8.403 mtr New Rail insert for removed
chipping on rail head
33 13/14.10.2022 30/177-179 UP MVNR - SAKT LR 9.02 ULC-40 9.02 mtr new rail pannel insert for
removed chipping on rail head
34 08/09.12.2021 32/19-21 UP SAKT-QM LR 8.341 ULC-45 8.341 mtr New Rail insert for removed
chipping on rail head
35 9/10.05.2022 32/49-53 UP SAKT-QM RR 9.17 STRAIGHT 9.17 mtr New Rail insert for removed
chipping on rail head
36 10/11.02.2023 32/37-1-37 UP SAKT-QM LR 6.944 ULC-45 6.944 mtr rail insert
37 14/15.02.2023 32/37-1-37 UP SAKT-QM LR 17.821 ULC-45 Removed defect & chipped-off rail &
insert 17.821 new rail.
38 05/06.08.2024 TO
09/10.08.2024
32/33B-37 UP SAKT-QM LR 24.88 STRAIGHT 24.88m rail Replacement
39 30/01.10.2022 33/65-67 UP QM-CHTP RR 8.343 ULC-49 8.343 mtr new rail pannel insert for
removed chipping on rail head
40 27/28.08.2023 TO
28/29.08.2023
33/25-29 UP QM-CHTP LR 43 STRAIGHT 43 mtr Rail pannel insert
41 18/19.01.2021 35/55-57 UP CHTP-SLTP RR 18 ULC-54 18 mtr rail panel insert
42 26/27.01.2021 35/39-41 UP CHTP-SLTP RR 18 STRAIGHT Approx 18 mtr rail panel insert
43 10/11.09.2022 35/37-39 UP CHTP-SLTP LR 9.8 STRAIGHT New extended leg 1:12 LH T/O LH
switch replaced at P02W due to
44 26/27..4.2023 35/21-25 UP CHTP-SLTP LR 43.007 ULC-53 43.007 mtr new pannel insert for
removed chipping on rail head
45 6/7.06.2023 35/11-13 UP CHTP-SLTP RR 36 ULC-52 36
46 14/15.06.2023 35/7-11 UP CHTP-SLTP RR 27 ULC-52 27
47 21/22.07.2023 34/41-49 UP CHTP-SLTP RR 117.1 ULC-51 117.1
48 17/18.10.2022 35/63-67 UP SLTP-GTNI LR 6.602 STRAIGHT 6.605 mtr new rail pannel insert for
removed pitted on rail
49 01/02.12.2022 36/13-15 UP SLTP-GTNI LR 6.5 STRAIGHT 6.5 mtr new rail pannel insert for
removed chipping on rail head
50 27/28.03.2021 41/57-59 UP AJG-GE RR 12 ULC-69 Approx 12 mtr rail panel insert
51 28/29.03.2021 41/37-51 UP AJG-GE RR 169 ULC-68 Appropx 169 mtr new rail pannel insert
52 10/11.04.2022 42/19-21 UP AJG-GE RR 18 ULC-70 18 mtr New Rail insert for removed
chipping on rail head
53 20/21.06.2022 42/25-29 UP AJG-GE LR 45 ULC-71 45 mtr New Rail insert for removed
chipping on rail head
54 27/28.06.2022 41/27-29 UP AJG-GE LR 18 ULC-71 18 mtr New Rail insert for removed
chipping on rail head
55 26/27.09.2023 TO
12/13.10.2023
41/67-59 UP AJG-GE LR 135.6 ULC-69 135.6m rail panel insert
56 03/04.11.2023 41/37-39 UP AJG-GE RR 6 ULC-68 6 mtr Rail insert
57 8/9.11.2023 41/51-53 UP AJG-GE RR 18 ULC-68 18 mtr Rail insert
58 18/19.05.2024 to
21/22.05.2024
43/09-13 UP GE - SKRP LR 46.59 ULC-74 10.59
59 05/06.07.2022 47/25-29 UP IFFCO - HCC LR 29.7 ULC-82 29.7 mtr New Rail insert for removed
chipping on rail head
60 13/14.12.2023 TO
14/15.12.2023
47/27-29 UP IFFCO- HCC LR 13.4 ULC-82 13.4 mtr Rail insert
61 21/22.12.2024 At P02Z(47/55-
53)
UP HCC D/E LR 5.852 POINT ZONE 5.852m Rail replacement work
62 29/30.04.2022 07/20-24 DN AZU-MDTW LR 36 DLC-8X 36 mtr New Rail insert for removed
chipping on rail head
63 06.06.2021 10/164-168 DN VW-VS LR 7.75 STRAIGHT Replacement of crossing P 7M
DN M/L BOC with all baseplate pad & 3
64 11/12.02.2022 11/24-26 DN VW-VS LR 9 DLC-1 Approx 150 mtr rail shifted towords
fracture location and 9 mtr new rail
65 19/20.09.2022 X06/009- 10/206 DN VW-VS LR 6.515 6.515 mtr new rail pannel insert for removed chipping on LH Rail P 10M
Diversion
66 08/09.01.2024 11/64-66 DN VW-VS LR 11.952 DLC-1 11.952 mtr Rail insert
67 24/25.03.2024 to
31/01.04.2024
10/236-242 DN VW-VS LR 38.184 DLC-1 38.184m rail insert
68 21/22.01.2021 14/178-180 DN KGM-CHK RR 9 DLC-9 9 Mtr rail panel insert at DLC -9 outer
rail
69 26/27.08.2021 14/42-44 DN KGM-CHK RR 18 STRAIGHT 18 m rail panel insert with removed 2
no chipping location & 1 no AT weld
70 12/13.07.2022 14/176-174 DN KGM-CHK LR 17.463 DLC-9 17.463 mtr New Rail insert for removed
chipping on rail head
71 13/14.07.2022 14/196-200 DN KGM-CHK LR 17.6 DLC-9 17.6 mtr New Rail insert for removed
chipping on rail head
72 05/06.01.2024 14/32-34 DN KGM-CHK RR 7.69 STRAIGHT 7.69 mtr Rail insert
73 20/21.6.2021 16/126-130 DN CWBR-NDI LR 18 DLC-15 18 m rail panel insert
74 21/22.6.2021 16/150-152 DN CWBR-NDI LR 18 DLC-15 18 m rail panel insert with removed 1
no AT weld defect at 16/148-150
75 15/16.09.2021 16/188-186 DN CWBR-NDI RR 11.15 DLC-16 11.15m rail panel insert with removed 1
no chipping location between 16/186-
76 11/12.03.2024 16/170-174 DN CWBR-NDI RR 6.9 DLC-16 6.9 mtr Rail insert
77 08/09.06.2024 TO
9/10.06.2024
16/142-148 DN CWBR - NDI 22.39 DLC-15 11.112 M RAIL REPLACEMENT
78 10/11.03.2024 18/10-14 DN NDI - RCK
DN line R hand SRJ of
RR 8.7 DLC-20 8.7 m rail insert due to weld crack found
79 12/13.07.2024 18/18-20 DN NDI - RCK Left Lead 12.1 DLC-20 12.1 m
80 25/26.10.2024 P03P LHS SRJ DN NDI-RCK LR 9.875 9.875m rail replacement work
81 17/18.11.2021 18/102-104 DN RCK-PTCK LR 7.941 DLC-22 18 mtr and 7.941 mtr new rail panel insert between 18/102-110 RCK-PTCK DN line due to replace of chipping on
rail head.
82 17/18.11.2021 18/108-110 DN RCK-PTCK LR 18 DLC-22
83 6/7.03.2022 18/120-130 DN RCK-PTCK LR 18 DLC-22 Insert 18 mtr rail pannel & removed chipping location
84 2/3.04.2022 18/114-112 DN RCK-PTCK RR 18 DLC-22 Insert 18 mtr rail pannel & removed defect DFWR weld but due to slow pouring 1 no weld found defective and
replace next day with insert 10.06 mtr
85 2/3.04.2022 18/116-118 DN RCK-PTCK RR 10.06 DLC-22
86 31/01.08.2023 19/30-34 DN RCK-PTCK LR 35.72 DLC-24 35.72 mtr new pannel insert for
removed chipping on rail head
87 19/20.09.2024 19/038-042 DN RCK-PTCK LR 24 DLC-24 24m Rail replacement work
88 1/2.03.2023 19/138-140 DN PTCK DN P/F
DN RR
RR 9.07 STRAIGHT 9.07 mtr new rail pannel insert for
removed chipping on rail head
89 12/13.08.2023 20/244-248 DN UDB-LKM LR 11 DLC-28 11 mtr Rail pannel insert
90 27/28.08.2023 TO
6/7.09.2023
20/246 TO
21/002-006
DN UDB-LKM LR 24 DLC-28 24 mtr Rail pannel insert
91 9/10.03.2022 26/86-88 DN AIIMS-GNPK
P 01U up
RR 5.8 DLC-37 5.8 m Rail new Rail insert for Removed DFWR weld
92 02/03.08.2022 27/54-56 DN GNPK-HKS LR 6.365 DLC-39 6.365 New rail pannel insert & removed
DFWR Weld between 27/54-56
93 04/05.08.2022 27/136-138 DN GNPK-HKS LR 8.3 DLC-39 8.3 mtr New rail pannel insert &
removed DFWR Weld between 27/54-
94 9/10.08.2021 28/92-94 DN HKS-MVNR RR 18 STRAIGHT 18 m rail panel insert with removed 1
no chipping location between 28/90-92
95 14/15.01.2022 28/196-198 DN HKS-MVNR RR 18 DLC-42 18 mtr New Rail insert for removed
chipping on rail head
96 25/26.05.2022 28/136-160 DN HKS-MVNR RR 116.45 DLC-41 116.45 mtr rail panel insert
97 15/16.07.2021 32/24-34 DN SAKT-QM LR 113.3 STRAIGHT Rail replacement between SAKT-QM DN
line left rail , OHE mast 32/24-34 total
98 06/07.12.2021 32/32-34 DN SAKT-QM LR 6.5 STRAIGHT 6.5 mtr New Rail insert for removed
DFWR weld
99 07/08.12.2021 32/24-26 DN SAKT-QM LR 9.3 STRAIGHT 9.3 mtr New Rail insert for removed
DFWR weld
100 23/24.12.2021 31/62-66 DN SAKT-QM RR 18 DLC-45 18 mtr New Rail insert for removed
chipping on rail head & 02 nos fish plate.
101 4/5.08.2023 TO
16/17.08.2023
33/24-34 DN QM-CHTP RR 78.5 DLC-50 78.5 mtr Rail pannel insert
102 18/19.08.2023 33/12-16 DN QM-CHTP LR 28.05 DLC-49 28.05 mtr Rail pannel insert
103 12/13.05.2023 35/22-28 DN CHTP-SLTP RR 78.5 DLC-56 78.5 mtr new pannel insert for removed
chipping on rail head
104 8/9.02.2021 36/6-8 DN SLTP-GTNI RR 8 DLC-58
105 14/15.09.2022 36/16-18 DN SLTP-GTNI LR 6.515 STRAIGHT 6.515 mtr new rail pannel insert for
removed chipping on LH Rail of 05W
106 13/14.04.2024 TO
27/28.04.2024
36/64-68 DN SLTP-GTNI LR 42.69 DLC-59 42.69 mtr replace for chipping
107 27/28.06.2024 to
3/4.07.2024
37/42-46 DN GTNI-AJG LR 46.154 DLC-62 54.5m RAIL REPLACEMENT
108 06/07.07.2024 to
9/10.07.2024
38/8-4 DN GTNI-AJG RR 54 DLC-63 54.0M Rail Replacement
109 23/24.07.2024 to
24/25.07.2024
37/60-38/4 DN GTNI-AJG RR 35.7 DLC-63 18m Rail Replacement
110 01/02.08.2024 39/32-34 DN GTNI-AJG RR 11.035 DLC-66 11.035 Rail replacement Work
111 24/25.04.2022 41/54-56 DN AJG-GE LR 8.4 STRAIGHT 8.4 mtr New Rail insert for removed
chipping on rail head
112 13/14.09.2023 TO
28/29.09.2023
41/62-74 DN AJG-GE LR 132.5 DLC-72 132.5 mtr Rail pannel insert
113 19/20.10.2023 42/14-16 DN AJG-GE LR 10.7 DLC-73 10.7mtr
114 22/23.10.2023 40/70-74 DN AJG-GE LR 27.12 DLC-69 27.12 mtr rail insert
115 15/16.04.2022 42/58-60 DN GE-SKRP LR 8.84 STRAIGHT 8.84 mtr New Rail insert for removed
chipping on rail head
116 2/3.05.2024 TO
8/9.05.2024
43/12-18 DN GE-SKRP LR 53 DLC-77 53 mtr rail insert for chipping removal
117 14/15.05.2024 43/12-14 DN GE - SKRP RR 13.72 DLC-77 13.72m For Chipping Removal
118 18/19.08.2024 45/62-64 DN MGRO - IFFCO RR 10.28 STRAIGHT 10.280m rail replacement work